The Red Line is a proposed light rail line for Baltimore, Maryland. The original project was granted federal approval to enter the preliminary engineering phase and the Maryland Transit Administration had spent roughly $300 million in planning, design and land acquisition, until Maryland Governor Larry Hogan declared his intent to not provide state funds for the project and shift state funding to roads in suburban areas. The original Red Line had been projected to cost roughly $1.6 billion, $900 million of which would have been guaranteed federal funding. Its construction had been estimated to begin in late 2015–early 2016, subject to funding, with a completion date set for late 2021–early 2022.
While campaigning for governor, Hogan characterized the project as a "boondoggle". Hogan's shift of state priorities to road funding resulted in the construction of several major projects near properties owned by his company, leading to allegations of corruption. The Red Line cancellation was briefly investigated by the United States Department of Transportation for being in possible violation of Title VI of the Civil Rights Act of 1964, since his decision shifted a large quantity of state money from predominantly Black and low-income neighborhoods into affluent and predominantly white areas, but the investigation was closed with no finding.
The project was classed as inactive; however, after several groups continued to campaign for its construction, governor Wes Moore, announced in June 2023 that the project had resumed. By that November, it was undergoing updated route evaluations and mode selection. Light rail was selected as the preferred mode in June 2024.
Background
In 2001, then-Maryland Secretary of Transportation John Porcari appointed a 23-member independent commission, the Baltimore Region Rail System Plan Advisory Committee, to make suggestions for new rail lines and expansions of existing lines. The proposals used a unified branding scheme for the existing lines and the proposed new lines, identifying each line by a color, as the Washington Metro and many other transit agencies do.
The suggested system was composed of six color-coded lines with an overall length of and 122 stations, including Baltimore's existing Metro SubwayLink and Light RailLink systems. In the commission's report, the Red Line was an east–west line that would begin at the Social Security Administration offices in Woodlawn in Baltimore County, travel through West Baltimore with an intermodal stop at the West Baltimore MARC station, pass through downtown (where transfers to the existing Metro Subway and Light Rail lines would be possible), and pass through East Baltimore with stops in Fells Point, Canton, and Patterson Park. The Red Line was designated by the commission as the starting component for new work on the 6-line system.
Out of the commission's various proposals, the Red Line was taken up with the most enthusiasm by area officials. Progress was slowed by a debate between state Secretary of Transportation Robert Flanagan and the Baltimore City government and Congressional delegation over the mode of transportation; Flanagan favored a bus rapid transit (BRT) solution with separate right-of-way components like Boston's Silver Line, while the city officials favored a light rail or heavy rail line and insisted that both modes of rail transit be included in studies.
Heavy rail was dismissed by Flanagan as an alternative, due to an estimated cost of $2.2 billion to $2.6 billion. With ridership of Baltimore's existing Metro system at only 45,000 at the time of his appointment, he did not expect the Red Line to reach the 140,000 to 150,000 ridership level necessary to attract federal funding for heavy rail.
Red Line alternatives
TSM: Transportation systems management (using the existing bus system, with modifications to signalling, lane assignments, and controls)
BRT: Bus rapid transit
LRT: Light rail transit
Modified alternative 4C selected by governor
In August 2009, then-Governor Martin O'Malley (who was also a former mayor of Baltimore) selected a modified version of the Light Rail Alternative 4C, which became known as the "Locally Preferred Alternative (LPA)." The modification eliminated two stations and a small parking lot from the original Alternative 4C plans, but included an expansion of parking at the West Baltimore MARC station.
Two features of the original Alternative 4C plan, considered important by the Citizens Advisory Council, remained part of the Locally Preferred Alternative:
Much of the proposed route through West Baltimore ran generally along U.S. Route 40, including the depressed freeway section left over from the cancellation of Interstates 70 and 170 within the city limits. This freeway section was built to accommodate a transit line in the median, and the Red Line would most likely have used this route to achieve grade separation though the area. The western end of former I-170 was demolished in 2010 to allow for additional parking and median access for the Red Line. A similar modification was also planned for the eastern end of former I-70, where the MD 122/Security Boulevard interchange would be converted to an at-grade intersection, and a new Park & Ride lot would have been built to replace the one that sits east of said interchange. At the rebuilt intersection, the Red Line would have gone through the western portal of the Cooks Lane tunnel, MD 122 would have tied directly into Forest Park Avenue, and Cooks Boulevard would have been a westward extension of Cooks Lane, built as a surface road on the old I-70 alignment. Although the modifications have not yet occurred, I-70 from MD 122 to I-695 was decommissioned in 2014 and now ends at its stack interchange with I-695; the freeway east of I-695 carries the unsigned designation of MD 570.
The LPA provided for the line to go underground along Martin Luther King, Jr. Boulevard and to surface on Boston Street near the Can Company in Canton, bypassing downtown Baltimore's narrow streets and crowded traffic conditions. Another tunnel bypasses Cooks Lane, but the original LPA version reduced the tunnel to a single track alignment. Adjustments to the LPA were later made to allow a second track in the Cooks Lane tunnel.
With the Federal Transit Administration's approval in June 2011 to start preliminary engineering, the project made its first step beyond the concept stage; however, the FTA estimated daily ridership for the completed system at 57,000 and expected it to cost a total of $2.2 billion with inflation included. Henry Kay, MTA's deputy administrator, estimated the cost of preliminary engineering at $65 million. The state would have had to pay preliminary engineering costs, but Kay said that these and other upfront costs would be eligible for federal reimbursement.
Cancellation and federal investigation
Governor Larry Hogan, who was elected in 2014, announced on June 25, 2015 that he had canceled funding for the Red Line. During his 2014 campaign, Hogan had complained about the cost of the proposed Red Line for Baltimore, calling it a "boondoggle", and a proposed Purple Line for the Maryland suburbs of Washington, DC; however, he ultimately allowed the Purple Line to begin construction with reduced funding.
Federal investigation
On December 21, 2015, the National Association for the Advancement of Colored People (NAACP), together with the American Civil Liberties Union of Maryland and Baltimore Regional Initiative Developing Genuine Equality (BRIDGE) filed a complaint pursuant to Title VI of the Civil Rights Act of 1964 with the U.S. Department of Transportation Departmental Office of Civil Rights. The complaint challenged Governor Hogan's decision to cancel the Red Line on the basis of discrimination against Baltimore's predominantly African American population that would have benefited from the infrastructure project. Furthermore, the complaint highlighted that Governor Hogan's decision shifted funding away from public transportation dependent citizens, and instead was dedicated towards highway projects in primarily white rural and suburban areas of the state.
On January 19, 2017, the last day of the Obama Administration, the Department of Transportation announced it expanded its investigation into Governor Hogan's decision to cancel the Red Line, as well as the rest of MDOT's programs to determine whether federal law was violated. In addition, the DOT stated that the state transportation agency did not take the federal law into account or the adverse impact it would have on African-Americans, nor did the Governor seek any input from MDOT in making the decision. In July 2017 the DOT announced that it was closing its investigation with no finding.
Proposed route and stations
The alignment for the Red Line would have followed an east–west path. Starting from the west, the proposed stations were as follows:
Notes:
A authorized employee parking only
F facility parking only
P paid parking
R residential parking only
Red Line system features
Plans revived
The Infrastructure Investment and Jobs Act contains a provision on project reentry which directs the United States Secretary of Transportation to "provide full and fair consideration to projects that seek an updated rating after a period of inactivity." This provision was sought by Maryland Senator Ben Cardin with the intent to allow for the Red Line and other canceled transit projects to be renewed. On June 15, 2023, Governor Wes Moore announced that he would restart efforts to build the Red Line in a ceremony with Baltimore mayor Brandon Scott. The state Department of Transportation plans to identify possible route alignments, gauge public feedback, and study the project's costs and benefits over the course of the rest of the year. In the meantime, the MTA will provide limited-stop bus service between Catonsville and Essex beginning in August 2023. MTA released six new alternative routes for the project that September – two alternatives featured tunnel segments and alignments similar to the canceled 2009 route. Officials initially did not say if the route would be run by bus rapid transit or light rail, but later announced in June 2024 that it will feature light rail.
In 2026, installation of bus lanes along the Red Line route began. The project was designed to improve service for the MTA CityLink Orange and Blue routes, and the QuickLink 40 route.
See also
Green Line – a proposed rail line in Baltimore from Johns Hopkins Hospital to Morgan State University.
Yellow Line – a proposed rail line from Hunt Valley to Columbia Town Center.
Charles Street Trolley – a proposed trolley line in northern Baltimore, backed by a non-MTA group.
References
External links